Tag Archives: Boat Refurbishment

Sanding Continued

Monday 02.07.2018

For a few hours after work spare I wanted to complete the sanding to the top deck/roof, there was only about 1/4 left to tick this job off.

Managed to get this completed as well as more sanding around the windows.

Advertisements

Rib Removal

Sunday 1 July 2018

Have received confirmation that the ribs will be delivered this week some time. So need to crack on and start preparing for the installation.

Today with Terry we started to remove every second rib in the second bay on the port side. Grinding off the old copper roves and punching out the copper nails. Will need to epoxy in some plugs where the old nails have been removed.

Will source the copper nails and roves this week also, expect these to cost as much as the ribs.

 

Sanding, scraping, vacuuming

20180103_180348Up to January 15, 2018

Update over Christmas and the New year period. Went for a week holiday to Fiji so not much done at all. Have however I removed the brass trim and started sanding the exterior. A bit of work to do here but the attachment to the grinder is working well and removing paint quickly.

It is all creating a lot of dust which is covering everything – the vacuum is getting a work out.

The upper deck levels where it has been glassed over looks as thought the glass is in very good condition, so may only need a light sand and patches where it is damaged and then a re-paint should do it.

I have also removed on of the port side glass panes, came out easily enough, these will all require re-glazing.

 

 

 

Pits and pieces

Update to 13 December 2017

Have completed the walkway platform around the boat, and am underway with the final strip out/off.

Removing brass trims, and fittings now we have a dry working area.

Have cleaned off the last of the moss etc. and dismantles the skylight. Back canopy doors have been removed (she looks like a different boat without these sliding doors).

Covers Complete! (5 months)

Weekend 25 & 26 November 2017

Its amazing what can be done when the weather clears up. On the Saturday I managed to install the covers to the front of the boat shed and place some more plywood on the floor – only 4 sheets to go then the floor will be complete also.

Sunday, with help from my father, we installed the cover over the rear section and framed a timber louvre to allow some air flow. We also did a tidy up and I built a step into the rear door. Just have a pair of doors to build now and the last few sheets of ply and we will be back onto the boat proper.

Some other small jobs completed were the removal of the scaffold from the rear entry and removal of the temporary roof from where the wheel house was removed. Just to say that I did work on the boat I also removed the sliding doors from the rear cabin and what was left of the fabric covers.

 

Covers Continued

19 November 2017

Again with help from Terry two more covers were placed over ANZAC. Just the ends now to complete the structures roof. Will look to install the floor soon.

20171121_070825

20171121_070713

I have used water filled drums as weights, with heavy duty straps to help weigh down the structure – reducing the risk of wind getting under the cover and lifting off.

20171121_070734

 

 

Covers Going On!

Sunday 12.11.2017

Finally the weather has started to calm down and some fine days have come along. With Terry’s help we managed to get two tarpaulin’s on the frame and secured down. Another couple of days like this we will be back onto working on Anzac properly!

20171113_083236

20171113_083130

The whole structure has been anchored to the ground by straps and large water filled drums – there will be 4 straps with 8 drums in total – one every second truss.

I decided to drape the tarpaulin’s over as opposed to along the structure – I figure I will save myself the cost of hiring a hoist to get the last tarp on.

20171113_083223