Tag Archives: Kauri

Covers Continued

19 November 2017

Again with help from Terry two more covers were placed over ANZAC. Just the ends now to complete the structures roof. Will look to install the floor soon.

20171121_070825

20171121_070713

I have used water filled drums as weights, with heavy duty straps to help weigh down the structure – reducing the risk of wind getting under the cover and lifting off.

20171121_070734

 

 

Covers Going On!

Sunday 12.11.2017

Finally the weather has started to calm down and some fine days have come along. With Terry’s help we managed to get two tarpaulin’s on the frame and secured down. Another couple of days like this we will be back onto working on Anzac properly!

20171113_083236

20171113_083130

The whole structure has been anchored to the ground by straps and large water filled drums – there will be 4 straps with 8 drums in total – one every second truss.

I decided to drape the tarpaulin’s over as opposed to along the structure – I figure I will save myself the cost of hiring a hoist to get the last tarp on.

20171113_083223

Boat Shed Continued

23 October 2017

The rain has continued – the result being only a few hours of work on the shed over the long weekend. Terry came around and helped me install the last of the bracing (4 bays). Stopping and starting between showers. During the week I also picked up the plywood which will form the floor.

We are now ready for the cladding to go up – hopefully the rain and wind will stop and we have a clear run to finish the temporary shed.

Weekend Update – Boat Shed

15 October 2017

This weekend (really Sunday only) Terry and I framed out the floor to the front section of the shed, completed the Northern side and framed the stern section floor.

20171015_174444

Since the weather was fine we also framed the stern wall and created the opening for a large pair of doors – these will be next weeks task along with the ply floor and remainder of the bracing.

20171015_174343

20171015_174407

 

Weekly Update – Boat Shed

October 2nd – 8th

With some time off and a break in the weather, I was able to spend some time on constructing the boat shed.

Firstly I had purchased some 220L plastic drums – 8No – which I intend to fill with water and use as weights to help secure the shed to the ground (as this is only a temporary structure). – I will show how this is to be done later.

I built a temporary platform to give me access to the last 2 trusses. I built the trusses and installed these all in one morning then continued framing out the floor ready for plywood.

The front curve frame was next – framed this up to give me enough space to be able to work around with sufficient room, dismantled the truss template and re-used these materials.

Started adding the strip bracing until I ran out of materials – have ordered some more so will complete the bracing this week.

20171007_181712

Jobs to complete the boat shed include;

  1. Install balance of bracing
  2. Frame out for plywood floor
  3. Install plywood flooring
  4. Frame end wall, with door opening and ventilation (Make doors)
  5. Install coverings – tarps to go on
  6. Install “tie downs” with weights

 

 

 

More Boat Shed Construction

Thursday 28.09.2017

Have managed to complete the floor framing on the port side, and construct and erect two more trusses complete with purlins. Also installed the nail plates across the top of the paired trusses – effectively fixing them together. Also cleaned up and sorted the remaining timber – so more room to maneuver the cars now.

Boat Shed Floor

Sunday 25.09.2017

Started framing out the port side shed floor, ready to take the plywood floor, will repeat the process on the starboard side. Also dropped into the timber merchants and purchased the last of the truss material – 4 more to go.

More Canopy Work

17.09.2017

FINALLY … back on ANZAC over the weekend (Sunday) – spent 4 hours with Terry putting up purlins, replaced a truss which was brought down by last weeks storm – a case of having put it in place (temporarily) 5 weeks ago as it started to rain thinking I would be back the next day to finish …. 5 weeks later the rain stops, but too late.

20170918_082857

We put the tarp back over the cockpit opening, I was hopping some of the rain and air would help air out the boat.

We have 4 trusses to go and the platform then we can cover her up.

Boat Shed Continued

Saturday 05.08.2017 – A few hours this morning – Took the tarp off ANZAC today, as the interior is stripped out and the boat is currently damp anyway – plus I did not want to fall through to opening where the wheel house has been removed – will fold this up ready for forming the roof.

 

I continued to install trusses – 3 of them – I will need to order some more materials for the more trusses (will need to make a further 3). Six trusses installed, seven to go!

Sunday 06.08.2017 – continued to make more trusses – made 3 today with Terry’s help. So have 4 ready for installation – we now have run out of truss material. Some of the trusses have got slight bows to them as well as the curve – a bit of a pain but  will have to do.