7 & 8 July 2018
Spent a few hours on Saturday and Sunday removing more ribs from ANZAC and cleaning up the inside of the hull.
I put the sander on to some of the interior structural timbers – the original builders used some beautiful timber when she was first built! I am also cleaning any paint from the interior side of the hull planks – this is much easier with the ribs out and is taking no time at all – it will look like new once the ribs are back in.
Rib removal is not very exciting but I am starting to see more progress. The stern section only requires 4 ribs to be replaced (as at some point this area has been replace recently) the other 3 sections we will replace them all, will be tricky around the engine beds.
The new rib material was delivered on Friday, so I dropped into the chandlery store to confirm the correct gauge copper nails – I will order these this week, but want to firstly re-count the number required. I also checked out the size of roves used – there appears to be a mixture used on ANZAC depending on where you look.
Will have a go at plugging the old nail holes this week.